Can I turn off RFI numbering by project stage in Procore once it is on?
Una pregunta, explicada al detalle.
No. Enabling Prefix RFI Numbers by Project Stage is irreversible, and Procore shows a confirmation dialog for that reason.
The setting lives on the project level RFI settings page, alongside default turnaround, overdue reminders, response visibility and the email notification matrix. Everything else on that page can be changed back. This one cannot.
Decide it before the first RFI is raised, because the prefix changes how every number reads and how anybody searching for one will find it. If you are unsure, leave it off: an unprefixed scheme can be lived with, and a prefixed one cannot be undone.
Cada frase resaltada arriba coincide exactamente con el texto que muestra la pantalla.
Hacer una pregunta de seguimiento
Esta es una consulta específica. Es probable que la suya sea la siguiente y trate sobre su propio modelo en lugar de este.
Limitado a Procore. 3 preguntas gratuitas sin necesidad de tarjeta.
Más información sobre Procore, o consulte todas las respuestas publicadas.